I seem to have lost track of what week it is… maybe it’s denial that we are more than 4 weeks past the initial goal that makes me want to bury my head in the sand?!? It’s actually week 12 and we have flooring! Hooray! Forward movement is progress and I am happy to have it!
The next hurdles are getting the granite & back splash in, refinishing the shower tile, getting appliances in & completing trim out work & the punch list so far. There is still some touch up painting to do as well.
They did get the exterior painted and the workshop painted red, too, since our last update.
We are over on holding costs putting us $5,000 behind on budget currently which we are adding to our other $1,500 of overage expenses. That has us $6,500 in the red on our budget. We will likely be over budget an additional $6,000 In holding costs & odds, ends that will need to be done. We aren’t going to turn the profit that we had hoped on this one and that’s why it’s important to flip multiple at a time! As always, we are learning great lessons on this one and will do the next one differently. It is coming together though and looking good!